<p n="77"> <note type="authorial" place="margin">Sept 8th. 1743.</note>
he will do and perform the said repairs in a good Substantial and<lb></lb>
Workman like manner and find & provide good sound Timber, Stone,<lb></lb>
Bricks, Iron, Gravel, and other Materials for that purpose, to the<lb></lb>
intent such proposal may be laid before the Court of Sessions of the <lb></lb>
Peace for the said County for their direction and in Order to have a <lb></lb>
proper contract and agreement in such behalf made, All which<lb></lb>
we Submitt to the Consideration of the Court</p>
<p n="78"> <rs type="persName" id="LMSMGO55602_n78-1">Ja: Clitherow</rs>
<interp inst="LMSMGO55602_n78-1" type="given" value="Ja"></interp>
<interp inst="LMSMGO55602_n78-1" type="surname" value="Clitherow"></interp>
<interp inst="LMSMGO55602_n78-1" type="gender" value="male"></interp>
<lb></lb>
<rs type="persName" id="LMSMGO55602_n78-2">Tho: Moore</rs>
<interp inst="LMSMGO55602_n78-2" type="given" value="Tho"></interp>
<interp inst="LMSMGO55602_n78-2" type="surname" value="Moore"></interp>
<interp inst="LMSMGO55602_n78-2" type="gender" value="male"></interp>
<lb></lb>
<rs type="persName" id="LMSMGO55602_n78-3">Richd. Ricards</rs>
<interp inst="LMSMGO55602_n78-3" type="given" value="Richd"></interp>
<interp inst="LMSMGO55602_n78-3" type="surname" value="Ricards"></interp>
<interp inst="LMSMGO55602_n78-3" type="gender" value="unknown"></interp>
</p>
<p n="79">The Estimate of the necessary Costs & charges for the repairing the <lb></lb>
Middx Side of <rs type="placeName" id="LMSMGO55602_geo200">Chertsea Bridge</rs>
<interp inst="LMSMGO55602_geo200" type="placeName" value="Chertsea Bridge"></interp>
<interp inst="LMSMGO55602_geo200" type="type" value="undefined"></interp>
</p>
<p n="80">To more off the Gravell on <rs type="placeName" id="LMSMGO55602_geo201">the Bridge</rs>
<interp inst="LMSMGO55602_geo201" type="placeName" value="the Bridge"></interp>
<interp inst="LMSMGO55602_geo201" type="type" value="undefined"></interp>
& digging against <rs type="placeName" id="LMSMGO55602_geo202">the Wharfing</rs>
<interp inst="LMSMGO55602_geo202" type="placeName" value="the Wharfing"></interp>
<interp inst="LMSMGO55602_geo202" type="type" value="undefined"></interp>
<lb></lb>
& brest of <rs type="placeName" id="LMSMGO55602_geo203">the Bridge</rs>
<interp inst="LMSMGO55602_geo203" type="placeName" value="the Bridge"></interp>
<interp inst="LMSMGO55602_geo203" type="type" value="undefined"></interp>
to make way for the putting down piles Land tyes, <lb></lb>
& Planking & filling up again and laying on the Gravell & bringing <lb></lb>
more to compleat the Gravelling <rs type="placeName" id="LMSMGO55602_geo204">the Bridge</rs>
<interp inst="LMSMGO55602_geo204" type="placeName" value="the Bridge"></interp>
<interp inst="LMSMGO55602_geo204" type="type" value="undefined"></interp>
to the Top of the <rs type="placeName" id="LMSMGO55602_geo205">Gravell</rs>
<interp inst="LMSMGO55602_geo205" type="placeName" value="Gravell"></interp>
<interp inst="LMSMGO55602_geo205" type="type" value="undefined"></interp>
<lb></lb>
Sill 6 Inches using and brest Work to the Road after the <rs type="occupation" id="LMSMGO55602_occ94">Carpenters</rs>
<interp inst="LMSMGO55602_occ94" type="occupation" value="Carpenters"></interp>
<lb></lb>
Work is finished.</p>
<p n="81">To take up the old posts Rails and Braces and lay them by and take <lb></lb>
up the Gravell Sills and all the planking and also the Joysts as lye <lb></lb>
over the Trussell heads as are to be taken out to drive down new <lb></lb>
piles being the 1st. 5th. 6th & 9th</p>
<p n="82">To drive down New piler that are wanting (Viz)LengthInches <lb></lb>
In the 1st. Ten of piles next the Wharf 1 New pile21 ft. 12 Sqr.<lb></lb>
5 Ten of piles next the Wharf 2 New pile28 ft. 12 Sqr.<lb></lb>
6 Ten of piles next the Wharf 1 New plie33 ft. 16 Sqr.<lb></lb>
9 Ten of piles next the Wharf 1 New pile36 ft. 16 Sqr.<lb></lb>
in all 5 New piles</p>
<p n="83">And to put on the Trussell heads again with two New ones that are <lb></lb>
wanting in the Room of two that are decayed 25 ft. Long each 13 by 12<lb></lb>
in the brest of <rs type="placeName" id="LMSMGO55602_geo206">the Bridge</rs>
<interp inst="LMSMGO55602_geo206" type="placeName" value="the Bridge"></interp>
<interp inst="LMSMGO55602_geo206" type="type" value="undefined"></interp>
9 New piles wanting 14 ft. Long each 1 ft.<lb></lb>
<rs type="occupation" id="LMSMGO55602_occ95">Sqr</rs>
<interp inst="LMSMGO55602_occ95" type="occupation" value="Sqr"></interp>
. & to plank behind them with the Old planking taken off the <lb></lb>
Bridge that shall be found sound & fit for the use</p>
<p n="84">To wharf the lower side of <rs type="placeName" id="LMSMGO55602_geo207">the Bridge</rs>
<interp inst="LMSMGO55602_geo207" type="placeName" value="the Bridge"></interp>
<interp inst="LMSMGO55602_geo207" type="type" value="undefined"></interp>
22 ft. in length with 15 New <lb></lb>
Piles cut & by 8 with 22 ft. of Camshed cut 12 by 6 & to plank the same <lb></lb>
with the old planking taken of <rs type="placeName" id="LMSMGO55602_geo208">the Bridge</rs>
<interp inst="LMSMGO55602_geo208" type="placeName" value="the Bridge"></interp>
<interp inst="LMSMGO55602_geo208" type="type" value="undefined"></interp>
with 4 Land keys, Needles <lb></lb>
& Stakes. a Return of 12 ft. to be done with Old Materials as is <lb></lb>
Sound & 22 ft. of Needleing 5 by 3 with Spikes and Workmanship.</p>
<p n="85">To fix down all the Joysts as shall be taken up and make good what <lb></lb>
shall be wanting with Nails & Workmanship.</p>
<p n="86">To 1540 ft. of 3 Inch Oak planking clear of Sap to the top of <rs type="placeName" id="LMSMGO55602_geo209">the Bridge</rs>
<interp inst="LMSMGO55602_geo209" type="placeName" value="the Bridge"></interp>
<interp inst="LMSMGO55602_geo209" type="type" value="undefined"></interp>
<lb></lb>
with Nails & Workmanship.</p>
<p n="87">To 220 ft. of Gravell Sill cut 14 by 6 clear from Sap fixed down in<lb></lb>
a Substantial manner with Nails & Work.</p>
<p n="88">To 220 ft. of Posts & Rails (Viz) the 4 Truss posts over the great Peir <lb></lb>
to be 7 ft. Long each 11 Inches Sqr. the 2 top Rails 9 ft. Long each<lb></lb>
9 by 8. 4 braces 11 ft. Long each 9 by 8. 24 posts 8 ft. Long each <lb></lb>
10 Inches Sqr. 12 braces 7 ft. Long each 9 by 3. 10 prick posts 4 ft. <lb></lb>
Long each 6 by 9. 202 ft. of top Railing 6 by 5 & 440 ft. of Small</p>