£ s d
To the Contract & Extra Carpenter Work 198.8.6 198.8.6
Dr. Bricklayers Work4.16.9
42 lt of framd Iron Straps & Staples to the
Chimney of the New Shed Mens Side5d. 0.17.6
66 lt of Lead to Gutter over Passage
leading to Chapel11.2
204.13.11
Received by old Iron, a part of the
Cheveaux de frieze & a Chimney Bar
C Q ld
Weight 7.3..15ld10s3..18..10
Dedt. Lead Gutter not done to Mens new
C Q ld
Day Shed Weight 1..1..1919s1.6.11
5..5.9
£ 199.8.2
Didnot mistakes1..11
£ 197.17.2
Examind Thoms Rogers< no role >
Allowed
I Paine
Sampn: Wright< no role >